Introduction
In a significant ruling reinforcing constitutional protection of private property, the Karnataka High Court has held that delay even extending over 65 years cannot extinguish a landowner’s right to just compensation when the State admits that it has taken over private land without following due legal process.
Why This Judgment Matters Reaffirms Article 300A: State cannot take private land without authority of law. Clarifies that delay or silence by landowners does not validate illegal State possession. Compensation is mandatory where land is taken without acquisition under the 2013 Land Acquisition Act. Sets an important precedent for old, pre independence or decades old government encroachments.
Court’s Key Observations
“No individual’s private property shall be wrested away by the State save through the due process ordained by law.” State’s act of occupying land without acquisition violates constitutional fibre. Admission of unauthorised use by the government automatically triggers right to compensation.
Summary of the Judgment:- The Karnataka High Court, per Justice M. Nagaprasanna, ruled that the State cannot deny compensation merely because the landowners did not approach the authorities for several decades. When the State admits that land was used without any legal acquisition, compensation under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”) becomes inevitable. The Court directed the Deputy Commissioner, Tumakuru, to determine and disburse compensation within three months.
Detailed Case Analysis:- Background of the Dispute:- Petitioners H.P. Ramesh and his daughter Sushmitha approached the High Court after the Deputy Commissioner rejected their claim for compensation. Ramesh had gifted the land to his daughter on 04.12.2017 through a registered deed. The land had been utilised as early as 1957 for construction of a government school and road. Multiple representations seeking compensation were ignored. A prior High Court order directing consideration resulted in a rejection, prompting the present writ petition.
Petitioners’ Stand:- The petitioners argued: The land was admittedly used by the Government. Construction of a school and road on private land is undisputed. Therefore, despite delay, compensation cannot be denied. The 2013 Act mandates fair compensation even for past acquisitions where no lawful procedure was followed.
State Government’s Defence:- The State contended: The land was voluntarily handed over in 1957. The landowners kept quiet for 65 years. Their right to seek compensation had extinguished under Section 27 of the Limitation Act, 1963. Since 12 years had passed, claims were legally barred.
Court’s Rejection of the State’s Argument:- Justice M. Nagaprasanna held that the Limitation Act cannot protect the State when it admits illegal occupation.
Key reasoning: The State conceded that the land was utilised without lawful acquisition. When the State takes land without authority, constitutional obligations override limitation. Public infrastructure built on private land does not erase the State’s duty to compensate.
The Court observed:
“When the State by its own hand has taken away the possession of the citizen’s private land… it must meet the threshold of justification by grant of compensation.”
Final Directions:- The Court ordered:- Compensation to be assessed under the 2013 Act, which provides higher benefits. Completion of the compensation determination process within three months. The State must ensure fair and lawful payment to the petitioners.
Case Reference Case Title: H.P. Ramesh & Anr. v. State of Karnataka & Anr. Case No.: Writ Petition No. 3982 of 2023 Court: Karnataka High Court Judge: Justice M. Nagaprasanna
Advocates:
For Petitioners: Advocate Kishan K.S
For Respondents: HCGP Rashmi Rao
Keywords
Karnataka High Court land compensation ruling delay in claiming compensation land acquisition Article 300A private property rights India unauthorized government land occupation Right to Fair Compensation and Transparency in Land Acquisition Act 2013 illegal state land acquisition compensation
Karnataka High Court 2025 judgments landowners rights India constitutional right to property India school constructed on private land compensation
- Minority Cannot Substitute Proof of Occurrence in Rape Cases: J&K and Ladakh High Court
Shivaji Rathore 14-Dec-2025 Jammu, The High Court of Jammu & Kashmir and Ladakh has ruled that where the prosecution fails to… Read more: Minority Cannot Substitute Proof of Occurrence in Rape Cases: J&K and Ladakh High Court - Compassionate Appointment Cannot Become a Claim for Higher Post: Supreme Court
Shivaji Rathore 13-Dec-2025 The Supreme Court on Friday (December 12) held that a person who has accepted a compassionate appointment cannot… Read more: Compassionate Appointment Cannot Become a Claim for Higher Post: Supreme Court - Supreme Court Issues Exhaustive Guidelines to Streamline 138 NI Act Cases: Mandatory Synopsis, Online Payment, No Pre – Cognizance Summons & More
Synopsis required for every 138 case filing, Landmark Judgment Shivaji Rathore 12 -Dec-2025 In a landmark ruling aimed at speeding up… Read more: Supreme Court Issues Exhaustive Guidelines to Streamline 138 NI Act Cases: Mandatory Synopsis, Online Payment, No Pre – Cognizance Summons & More - Jammu & Kashmir High Court Reiterates: Revenue Authorities Cannot Proceed When Civil Court is Already Seized of the Dispute
Shivaji Rathore 12-Dec-2025 In a significant ruling reinforcing judicial discipline between parallel forums, the High Court of Jammu & Kashmir and… Read more: Jammu & Kashmir High Court Reiterates: Revenue Authorities Cannot Proceed When Civil Court is Already Seized of the Dispute - SC: Cash Transactions Above ₹20,000 Do Not Make Debt Unenforceable Under Section 138 NI Act
Supreme Court Sets Aside Kerala HC View Declaring Cash Loans Above ₹20,000 as “Not Legally Enforceable Debt Shivaji Rathore, 11 Dec… Read more: SC: Cash Transactions Above ₹20,000 Do Not Make Debt Unenforceable Under Section 138 NI Act
This article cover the legal point whether compensation can be claimed after lot of time has gone when state has taken land state has acquired land from private person he is still Entitle for compensatio .further you can read here important judgements and legal principles laid down by Hon’ble supreme court of India, this article is posted by Advocate Shivaji Rathore (J&K high court jammu) for more important legal topics stay connected with us, on tacit legal we post on YouTube channel also named as Tacit Legal helpful for Law students newely enrolled Advocate in India and other states, Follow us on Instagram also, Read our articles on important Questions of Law. #tacitlegal visit my website Tacit Legal dot in search on google, this website is made from Hostinger and wordpress follow our latest updates for legal news follow us on YouTube also for young lawyers law students helpful for Advocates, this blog is written by Advocate Shivaji Rathore practicing in Jammu and Kashmir high court and district court at Jammu. The website Tacit Legal is available on Google created with Hostinger and wordpress keep in touch and read our daily articles and reporting for law students and advocates as we provide you important legal information on Tacit Legal.in
Author: Advocate Shivaji Rathore
Founder – Tacit Legal | tacitlegal.in